How to get a permit for a metal building
You don't need a permit to order a metal building. You order first, because the permit needs stamped drawings for your exact building. Here is the whole process step by step, from your order and design to the sealed blueprints your building department asks for.
"I don't have my permit yet" is the most common thing we hear from buyers, and it is the right order of things. Your building department issues the permit against stamped drawings for the building you are actually putting up: its size, its doors and windows, and your site's loads. Those drawings are engineered once your building is ordered and designed.
So the permit comes after the order, never before it. Once you order, we take you through the design, confirm your codes with your building department, and hand you the stamped blueprints, anchor bolt patterns and reaction plans your permit application needs. Your deposit covers that engineering, and your price is locked at order.

How to get a metal building permit, step by step
The same eight steps for a backyard shop, a farm building or a commercial building. The order matters: the building is ordered and designed first, because the permit is issued against its stamped drawings.
- 01
Get your quote
Tell us where the building is going, the size you want and what it is for. Your address is what the engineering is built on.
- 02
Order your building
Your order starts the engineering. Your deposit covers the engineering and approvals, and your price is locked at order.
- 03
Design it to the inch
We take you through the design phase: every door and window placed to the exact inch where you want it, and your wall, trim and roof colors chosen.
- 04
Approve your design
You sign off on the design. That approval is what the engineering is built from.
- 05
We confirm your codes with your building department
We contact your building department to confirm the wind, snow, seismic, live, dead and collateral loads for your site, so the building is engineered to exactly what your county requires.
- 06
Receive your stamped blueprints
Your building is engineered to those loads and you receive blueprints stamped in your state, with anchor bolt patterns and reaction plans. They are included in your building price.
- 07
Apply for your permit
You or your contractor submit the stamped blueprints with your site plan, your foundation design (drawn from our reaction plans) and the department's application form.
- 08
Pour, build and pass inspections
Your foundation is poured to the anchor bolt pattern, the building goes up, and your building department inspects it against the approved drawings.
What a building department asks for
Most metal building permit applications are built from these documents. The biggest one comes with your building.
Stamped blueprints
The engineered drawings for your building, stamped in your state and engineered to your site's loads. Included in every Stonebolt building price.
Anchor bolt patterns and reaction plans
Included with your blueprints. Your foundation engineer or concrete contractor designs the slab and footings from them.
Foundation design
The slab and footings, designed for your building from our reaction plans.
Site plan
Where the building sits on your parcel: property lines, setbacks, the driveway or access, and other buildings.
Permit application
The department's own form and fee, with the owner or contractor details.
Zoning approval
In some places a separate sign-off that the use and placement are allowed, often handled at the same counter.
Shop, farm or commercial: which path you are on
A shop, garage or storage building
Usually a residential or accessory building permit. Your stamped blueprints, foundation design and site plan are what the department reviews.
A farm or agricultural building
Many counties offer an agricultural exemption from the building permit for buildings used for farming, usually applied for through the county. Your stamped blueprints are valuable either way: they are what your insurer, your lender and a future buyer look for.
A commercial building
A commercial building permit, often with fire and accessibility review of how the building is occupied. The structural blueprints are the same stamped set; your architect or design professional handles the occupancy side, and we coordinate the building with them.
Who does what
The building
- The design phase: doors, windows and colors placed to the inch
- Confirming your codes and loads with your building department
- Blueprints stamped in your state, with anchor bolt patterns and reaction plans
- The building kit, delivered to your site
You or your contractor
- The permit application, site plan and fees
- The foundation design and concrete
- Zoning approval, where it is separate
- Erection and the inspections
You or your contractor file the permit. Everything on the building side of the application comes from us.
What to tell us before a quote
Four answers and we can quote your building and start your engineering as soon as you order.
- 1The address where the building is going
- 2Width, length and eave height, or what has to fit inside
- 3What the building is for: shop, storage, farm, commercial or living space
- 4Where you want your doors and windows, if you already know
Questions people ask
Do I need a permit before I order a metal building?
No. You order first, then get your permit. Your building department issues the permit against stamped drawings for your exact building, and those are engineered after you order and approve your design. Once you approve it, we confirm your codes with your building department and send you the stamped blueprints, anchor bolt patterns and reaction plans your application needs.
Do I need a permit for a metal building?
Almost always for a permanent steel building. Most counties and cities require a building permit, and some exempt farm buildings or very small sheds. Every Stonebolt building comes with blueprints stamped in your state for the application.
What drawings do I need for a metal building permit?
Stamped structural blueprints for the building, a foundation design and a site plan. Stonebolt includes the stamped blueprints in the building price, with the anchor bolt patterns and reaction plans your foundation is designed from.
When do I get my blueprints?
After you order and approve your design. We take you through the design phase, contact your building department to confirm your codes and loads, engineer the building, and send you blueprints stamped in your state.
Who applies for the building permit?
You or your contractor file the application. We do the building side: confirming your codes with your building department and providing the stamped blueprints, anchor bolt patterns and reaction plans.
Do I need a permit for a metal building on farm land?
Many counties exempt buildings used for farming from the building permit through an agricultural exemption, usually applied for through the county. Stamped blueprints are worth having either way for insurance, financing and resale.
Why there are no numbers on this page
No permit fees, review times or code figures. Those are set by your county or city, and we confirm yours with your building department after you order. The engineering numbers for your building come out on its stamped blueprints.