Learn
Mining and oil field buildings: maintenance shops
Shops for haul trucks, rigs and heavy equipment. Why height and lifting decide everything, where a pre-engineered building fits, and where it stops being the right answer.
A maintenance shop for a mine or an oil field is a truck shop scaled up: the machines are bigger, the doors are taller, and lifting is part of every job. The building has to clear a raised dump body or a mast, carry the cranes that pull engines, and stand up to remote sites and hard weather.
Steel pre-engineered buildings handle a lot of this well. Very heavy cranes are where they reach their limit, and we will tell you up front if your cranes need something else.

What decides the building
The biggest machine, at full height
A haul truck with its body raised or a rig with its mast up sets the clear height and the door height. Measure the machine in the position it is serviced in.
Cranes
Light and moderate cranes run on brackets on a pre-engineered frame. Very heavy cranes usually call for separate crane columns or a conventional steel building — we will tell you which your cranes need.
Bays and doors
Drive-through bays, tall doors on both ends, and room to walk around a machine with the hood open.
Wash bay and lube
Wet, dirty and often a separate bay or building, with its own drainage and ventilation.
Remote site and freight
Delivery to a remote site and erection with limited equipment favor a kit that arrives complete and bolts together.
Weather
Remote sites often see the hardest snow, wind and cold. The design loads come from the address — sometimes a very exposed one.
Where a pre-engineered building fits
A good fit
Service shops, warehouses, wash bays, offices and storage on a mine or field site, with light to moderate cranes.
Talk to us
Very heavy cranes, shops that stack several cranes on one runway, or process buildings with heavy equipment hung from the structure. These may need separate crane columns or a different kind of steel building, and we will say so.
Who does what
The building
- The steel frame engineered for your machines, doors and cranes
- Roof and wall panels, trim and framed openings as specified
- Stamped drawings sealed in your state, and the reaction plan
- Freight to the site, included
Other trades
- The cranes, runway power and hoists
- Doors, unless quoted
- Wash-bay drainage, lube systems and compressed air
- Foundation, erection and site work
What to tell us before a quote
Seven answers. The first two decide most of the building.
- 1The largest machine and its height in the serviced position
- 2Every crane or hoist, its capacity and how often it lifts
- 3Number of bays, and drive-through or back-in
- 4Wash bay, lube bay or tire bay
- 5Site location and access for delivery
- 6Offices, parts storage or a mezzanine
- 7Future bays or a second building
Questions people ask
What buildings does a mine site need?
Typically a truck and equipment maintenance shop, a wash bay, warehouse and parts storage, a tire shop, offices and dry facilities. Many of these fit pre-engineered steel buildings well.
How tall should a haul truck shop be?
Tall enough for the largest truck with its body fully raised, plus the crane that services it. Measure the machine in the position it is worked on, then add the crane and clearance.
When is a pre-engineered building not the right answer?
When cranes get very heavy, several cranes share one runway, or heavy process equipment hangs from the structure. Those may need separate crane columns or a different kind of steel building, and we will say so at the start.
Why there are no numbers on this page
No heights, crane capacities, loads or door sizes. Every one of those depends on your building, your site and your design loads, so we work them out for your building instead of publishing a chart. They come out of the engineering, on the sealed drawings for your building.
Ready to price your building?
Most Stonebolt projects start around $24,000 and run from 30 × 40 up. If that fits your budget, we'd like to hear about your project.