Crane buildings: a metal building with an overhead crane

What we need to know about the crane to engineer the building, why the hook height sets the eave rather than the other way round, and what to have ready when you ask for a quote.

An overhead crane is part of the building, not an accessory. Everything it lifts, and everything it weighs, goes through the building's frame to the ground, so we engineer the frame for your crane and show it on the drawings.

If a crane might come later, tell us on the quote form. We design the columns, brackets and bracing for it now, so adding the crane is straightforward.

Our 3D model of a steel building with two bridge cranes side by side: a yellow crane girder with its hoist and hook spanning between runway beams on brackets
Two bridge cranes side by side, one in each half of the building, from our own 3D model.

Six things about the crane that decide the building

The footprint matters less than you would expect. These six shape the frame.

01

How much it lifts

The rated capacity, plus what the crane itself weighs. Together they set how hard every wheel presses on the runway, and that load goes straight into the columns and down to the foundation.

02

How far it spans

The distance from one runway rail to the other. It is usually most of the building's width, and it decides whether one crane covers the floor or two cranes work side by side with a row of columns between them.

03

How high the hook has to reach

The lowest point the hook rises to is the height you can actually lift under. It is the number the whole building is worked backward from — see below.

04

Top-running or underhung

Whether the crane rides on rails on top of runway beams carried by the columns, or hangs from beams hung off the roof frames. Different load paths, different frames.

05

Single girder or double girder

One main beam with the hoist hanging under it, or two beams with the hoist riding on top between them. The choice changes how much hook height a given building gives you.

06

How hard it works

Occasional lifts in a maintenance shop and continuous lifting on a production line are different cranes and different buildings. Crane makers grade this as a service class; tell us how often it lifts and how heavy a typical lift is.

Hook height sets the eave, not the other way round

We work the height out from the floor up, in this order, so the building gives you the hook height you need:

  1. 1The hook — the height you need to lift to, measured to the bottom of the hook at its highest
  2. 2The hoist — the hoist body and hook block above it
  3. 3The bridge — the crane girder the hoist runs on
  4. 4The rail and runway beam — what the crane's wheels ride on
  5. 5Clearance — the gap the crane maker requires above the crane
  6. 6The roof frame — only then the eave, and the frame's depth at the wall

Each layer takes real height, and we count every one. When we drew a crane building in our own 3D model, every part of the crane was drawn at its real size, which is how we work out the hook height for yours.

The girder type moves the answer. On a single-girder crane the hoist hangs under the girder; on a double-girder crane it rides on top, between the two, so the same building gives you a higher hook. If height is tight, we work it through with you and your crane supplier.

Top-running, underhung or gantry

Three ways a crane is carried. The difference that matters to the building is what holds the crane up.

Top-running bridge crane

The bridge rides on rails fixed to the top of runway beams, and the runway beams sit on brackets on the building's columns. The columns carry everything the crane does.

The usual answer for heavier lifting and wider spans in a steel building. The frame is designed for it from the start: heavier columns, a bracket at every frame line, and bracing for the crane's travel.

Underhung crane

The crane's wheels run on the bottom flange of beams that hang from the roof frames. Nothing stands on the floor and the columns stay clear.

Suits lighter loads and keeps the floor open. The roof frames carry the crane, so we design them for it, same as a top-running crane.

Gantry crane

A crane on its own legs, rolling on the floor or on rails set in it. It is its own structure.

The building does not carry it, which is the whole appeal when a crane is light, moveable or added later. The slab still does, and the building still has to be tall enough for it to work under.

Pole barns and post-frame buildings come up in the same searches. A crane puts heavy, moving, repeated loads into the structure, and that is where a rigid steel frame designed for it earns its place — it is worth asking anyone who offers a crane in a post-frame building exactly what carries it.

Who does what

The building

  • A frame engineered for the crane loads you give us
  • Columns, brackets and bracing designed for the crane
  • Stamped drawings, sealed in your state
  • Foundation reactions that include the crane

The crane supplier

  • The crane, hoist and controls
  • The crane's data: wheel loads, wheel spacing, clearances
  • Power to the crane along the runway
  • Installation, load testing and inspection

We can supply the brackets, runway beams, rail, end stops and crane bracing with the building. Whether each one is included is written on your quote or purchase agreement. The crane itself comes from a crane supplier.

The two sides have to exchange numbers. The crane maker's wheel loads and clearances go into our engineering; our frame and its deflection limits go back to them. Send us the crane maker's data and we design the building around it.

Overhead cranes also have operating, inspection and testing rules of their own. Those belong to the crane, its supplier and its owner rather than to the building, so this page leaves them to them.

What drives the cost

A crane has its own price, and it changes the price of the building around it. How much depends almost entirely on the crane. Tell us about yours on the quote form and your quote is built around it.

Crane capacity

Heavier lifts mean heavier wheel loads: deeper columns, bigger brackets and bigger footings. The single biggest lever.

Hook height

Every foot of hook is a foot of eave, wall and column. Ask for the height you will actually lift to.

Span and layout

One crane across the whole width, or two side by side with columns between them, are different frames with different costs.

Runway length

Run the runway only where the work happens. We can run it over just the bays where you lift.

Usually quoted separately

  • The crane itself — bridge, hoist, end trucks and controls, from the crane supplier
  • Runway beams, rail and end stops — we can supply them; your quote or purchase agreement says whether they are included
  • Power to the crane along the runway, and the electrical work to feed it
  • Crane installation and load testing, usually by the crane supplier
  • The foundation, designed from our reaction plan and poured by your contractor

Published kit prices →

Questions people ask

What is a crane building?

A steel building engineered to carry an overhead crane: runway beams on brackets along the columns, heavier columns, bracing for the crane's travel, and footings sized for the crane's loads. The crane is part of the frame, not an accessory bolted into a finished building.

How much does a building with an overhead crane cost?

The crane changes the building's price as well as adding its own. Capacity, hook height, span and how much of the building the crane covers drive the building side; the crane, power and installation are usually separate quotes. We can supply the runway beams and rail, and your quote says whether they are included. Our published kit prices by size are on the Pricing page, and a quote prices the building for your crane.

What is the difference between a top-running and an underhung crane?

A top-running crane rides on rails on top of runway beams carried by the building's columns. An underhung crane hangs from beams fixed to the roof frames, so the roof frames carry it. Top-running cranes usually suit heavier loads and wider spans; underhung cranes keep the floor and columns clear for lighter loads.

Can I add an overhead crane to an existing metal building?

Only if the building was designed for it, or after an engineer checks and usually reinforces the columns, adds brackets and bracing, and checks the footings. If a crane might come later, tell us when you order and we design the frame for it.

How much hook height will I get?

Work it from the floor up: the hook height you need, then the hoist, the crane girder, the rail and runway beam, the crane maker's clearance and the roof frame. We work those layers out for your crane, and a double-girder crane gives more hook than a single-girder crane in the same building.

What to tell us before a quote

Eight answers. The last one lets us design for a crane you may add later.

  • 1The crane's capacity, and how many cranes
  • 2Where it runs: the full length of the building, part of it, or one bay
  • 3The height you need to lift to under the hook
  • 4Top-running, underhung or gantry, if you know
  • 5How often it lifts, and how heavy a typical lift is
  • 6Whether two cranes share one runway or work side by side
  • 7Who is supplying the crane, if you have chosen — their data sheet is an input to our engineering
  • 8Whether a crane might come later, even if it is not in this order

Why there are no numbers on this page

No capacities, no clearances, no hook heights, no beam sizes. Every one of them depends on your crane, your building and your site, so we work them out for yours. Your crane supplier's data sheet and our sealed drawings are where the numbers belong.